Installation of HDMI Infrastructure and Short-distance Datashows

Installation of HDMI infrastruture (cable): 72
Renovated Classrooms: 72 100%
Installation of HDMI infrastruture (switch): 72
Switches installed: 72 100%
Installation of short-distance datashows: 53
Video projectors installed: 53 100%
Installation of existing video projectors: 30
Video projectors installed: 36 83%

 

Objective: To modernize Iscte’s classrooms by replacing analogue video cabling (VGA) with digital (HDMI), as well as installing short-throw video projectors.

These interventions will, however, have an impact on day-to-day life, so we hope we can count on the understanding of the entire community.

Work Done

Friday, February 28, 2025

Planned:

Executed:

Planned:

    • Building 1 – JJ Laginha
    • Buildings 2 – C7-07 (awaiting completion of roof repairs – inflitration)

Executed:

    • Buildings 1 – JJ Laginha  (The HDMI cables for the TVs still need to be laid next Friday)
    • Buildings 2 – 

Planned:

Executed:

Planned:

Executed:

Planned:

Executed:

Planned:

Executed:

Planned:

Executed:

  •  

Planned:

Executed:

Planned:

Executed:

Planned (5):

Building 2

Executed (3/5):

Building 2

    • C7.06
    • C7.08
    • C7.09

Planned (8):

Building 2

Executed (4/8): 

Building 2

    • C6.06
    • C6.09
    • C7.05
    • C7.10

Planned (3):

Building 2

Executed (0/3):

Planned (6):

Building 2

Executed (0/6):

Planned (5):

Building 2

Executed (0/5):

3 Videoprojectors:

Building 1

Building 2

    • C2.05

Planned (5):

Building 1

Executed (5/5):

Building 1

2 Video projectors

Building 2

Planned (10): 

Executed (3/10):

Planned (10):

Executed (3/10): 

Planned (9):

Executed (5/9): 

Planned (7):

Executed (3/7):