Atualizado/Updated: 2025-03-18
								
				Installation of HDMI infrastruture (cable): 72			
		
		
			
						
				
				Renovated Classrooms: 72
									100%
							
		
								
				Installation of HDMI infrastruture (switch): 72			
		
		
			
						
				
				Switches installed: 72
									100%
							
		
								
				Installation of short-distance datashows: 53			
		
		
			
						
				
				Video projectors installed: 53
									100%
							
		
								
				Installation of existing video projectors: 36			
		
		
			
						
				
				Video projectors installed: 36
									100%
							
		
Objective: To modernize Iscte’s classrooms by replacing analogue video cabling (VGA) with digital (HDMI), as well as installing short-throw video projectors.
These interventions will, however, have an impact on day-to-day life, so we hope we can count on the understanding of the entire community.
Work Done
					 Friday, February 28, 2025 
							
			
			
		
						
				Planned:
- Building 1 – Caiano Pereira, Mário Murteira
 - Buildings 2 – C7-07 (awaiting completion of roof repairs – inflitration)
 - Building 3 – AA3.40
 
Executed:
- Building 1 – Caiano Pereira, Mário Murteira
 - Buildings 2 – C7-07 (awaiting completion of roof repairs – inflitration)
 - Building 3 – AA3.40
 
					 Tuesday, February 25, 2025 
							
			
			
		
						
				Planned:
- Building 1 – JJ Laginha
 - Buildings 2 – C7-07 (awaiting completion of roof repairs – inflitration)
 
Executed:
- Buildings 1 – JJ Laginha (The HDMI cables for the TVs still need to be laid next Friday)
 - Buildings 2 –
 
					 Sunday, February 23, 2025 
							
			
			
		
						
				Planned:
- Building 1 – Paquete de Oliveira, Caiano Pereira, Mário Murteira
 - Buildings 2 – C4.01, C4.02, C4.06, C4.07, C5.05
 - Building 3 – AA3.40
 
Executed:
					 Saturday, February 22, 2025 
							
			
			
		
						
				
					
					 Friday, February 21, 2025 
							
			
			
		
						
				
					 Thursday, February 20, 2025 
							
			
			
		
						
				
					
					 Wednesday, February 19, 2025 
							
			
			
		
						
				
					
					 Tuesday, February 18, 2025 
							
			
			
		
						
				
					
					 Sunday, February 16, 2025 
							
			
			
		
						
				
					
					 Saturday, February 15, 2025 
							
			
			
		
						
				
					
					 Friday, February 14, 2025 
							
			
			
		
						
				
					
					 Thursday, February 13, 2025 
							
			
			
		
						
				
					
					 Monday, February 10, 2025 
							
			
			
		
						
				Planned (5):
Building 2
Executed (0/5):
3 Videoprojectors:
Building 1
Building 2
- C2.05
 
					 Sunday, February 9, 2025 
							
			
			
		
						
				
					
					 Saturday, February 8, 2025 
							
			
			
		
						
				Planned (23):
- Building 1 – 1E04, 1E06, 1E08, 2E02, 2E03, 2E10, Caiano Pereira, Mário Murteira, Paquete de Oliveira, Auditório 1, Auditório 2, Auditório 4, JJ Laginha
 - Building 3 – AA2.23, AA2.24, AA2.25, AA2.26, AA2.29, AA3.23, AA3.29, AA3.30, AA340, Afonso de Barros
 
Executed (5/23):
- Building 1 – 2E02, 2E03, 2E10, Auditório 2, Auditório 4
 
					 Friday, February 7, 2025 
							
			
			
		
						
				
					
					 Thursday, February 6, 2025 
							
			
			
		
						
				Planned (10):
- Building 1 – 2E03, 2E04, 2E05, Caiano Pereira, Mário Murteira, Paquete de Oliveira, Auditório 1, Auditório 2, Auditório 4, JJ Laginha
 - Building 3 – Afonso de Barros
 
Executed (3/10):